[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166778":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1166778,829,1,"单选题","承包人和劳务分包人的劳务分包合同签订的流程根据合同（ ）的不同而不同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当事人约定",false,{"key":16,"text":17,"correct":18},"B","发包方式",true,{"key":20,"text":21,"correct":14},"C","合同性质",{"key":23,"text":24,"correct":14},"D","劳务工作量","承包人和劳务分包人的劳务分包合同签订的流程根据合同发包方式的不同而不同。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]