[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1166761,829,1,"单选题","劳务项目负责人应是劳务分包人正式聘用的员工，劳务分包人应向承包人提交项目负责人与劳务分包人之间的劳动合同，以及劳务分包人为项目负责人（ ）的有效证明。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发放工资",false,{"key":16,"text":17,"correct":14},"B","发放劳保用品",{"key":19,"text":20,"correct":21},"C","缴纳社会保险",true,{"key":23,"text":24,"correct":14},"D","确定双方关系","项目负责人应是劳务分包人正式聘用的员工，劳务分包人应向承包人提交项目负责人与劳务分包人之间的劳动合同，以及劳务分包人为项目负责人缴纳社会保险的有效证明。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]