[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1166736,829,1,"单选题","2013版《建设工程施工劳务分包合同（示范文本）》明确约定了承包人不得要求劳务分包人提供或采购（ ）、主要材料。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大型机械",true,{"key":16,"text":17,"correct":18},"B","辅助材料",false,{"key":20,"text":21,"correct":18},"C","设备",{"key":23,"text":24,"correct":18},"D","小型机械","2013版《建设工程施工劳务分包合同（示范文本）》明确约定了承包人不得要求劳务分包人提供或采购大型机械、主要材料。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]