[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1166717,829,1,"单选题","某机电安装公司2013年10月发生施工材料费用60万元，人工费25万元，机械使用费用5万元，财产保险费5万元。根据企业会计准则及其相关规定，则此项工程成本是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30万元",false,{"key":16,"text":17,"correct":14},"B","65万元",{"key":19,"text":20,"correct":14},"C","90万元",{"key":22,"text":23,"correct":24},"D","95万元",true,"工程成本=施工材料费+人工费+机械使用费+财产保险费=60+25+5+5=95（万元），故选项D正确。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]