[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1166703,829,1,"单选题","下列有关建造合同收人和成本内容的表述不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建造合同收人包括合同中规定的初始收人和因合同变更、索赔、奖励等形成的",false,{"key":16,"text":17,"correct":14},"B","因合同变更、索赔、奖励等形成的收人不构成合同初始收人",{"key":19,"text":20,"correct":14},"C","建造合同成本包括从合同签订开始至合同完成止所发生的、与执行合同有关的直接费用和间接费用",{"key":22,"text":23,"correct":24},"D","如果建造合同的结果不能够可靠地估计，企业不应当确认合同收人和费用",true,"如果建造合同的结果不能可靠地估计，就不能根据完工百分比法确认合同收人。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]