[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1166635,829,1,"单选题","对劳务分包队伍进行考核评价应由（ ）组织开展。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经理部",true,{"key":16,"text":17,"correct":18},"B","生产管理部门",false,{"key":20,"text":21,"correct":18},"C","劳务管理部门",{"key":23,"text":24,"correct":18},"D","经营管理部门","对劳务分包队伍进行考核评价应由项目经理部组织开展。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]