[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166464":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1166464,829,1,"单选题","施工项目成本控制的步骤包括：①纠偏、②分析、③检查、④比较、⑤预测，正确的步骤顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","④③②①⑤",false,{"key":16,"text":17,"correct":18},"B","④②⑤①③",true,{"key":20,"text":21,"correct":14},"C","②③④①⑤",{"key":23,"text":24,"correct":14},"D","②④⑤①③","施工项目成本控制的步骤为：比较、分析、预测、纠偏、检查",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]