[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1166454,829,1,"单选题","进行工程项目分解，确定阶段控制目标，是施工项目管理内容中的（ ）的内容之一。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工项目目标控制",false,{"key":16,"text":17,"correct":14},"B","建立施工项目管理组织",{"key":19,"text":20,"correct":14},"C","施工项目合同管理",{"key":22,"text":23,"correct":24},"D","编制施工项目管理规划",true,"施工项目管理规划的主要内容有：进行工程项目分解，确定阶段控制目标，然后从局部到整体实施和管理；建立施工项目管理工作体系，确定管理工作流程；建立系统文件，以利执行；施工项目的目标控制",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]