[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166437":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1166437,829,1,"单选题","下列各项措施中，不属于施工项目质量控制的措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","提高管理、施工及操作人员自身素质",false,{"key":16,"text":17,"correct":14},"B","提高施工的质量管理水平",{"key":19,"text":20,"correct":21},"C","尽可能采用先进的施工技术、方法和新材料、新工艺、新技术，保证进度目标实现",true,{"key":23,"text":24,"correct":14},"D","加强施工项目的过程控制","施工项目质量控制的措施：1）提高管理、施工及操作人员自身素质；2）建立完善的质量保证体系；3）加强原材料质量控制；4）提高施工的质量管理水平；5）确保施工工序的质量；6）加强施工项目的过程控制。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]