[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166415":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1166415,829,1,"单选题","下列措施中，不属于施工准备阶段的安全技术措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","技术准备",false,{"key":16,"text":17,"correct":14},"B","物资准备",{"key":19,"text":20,"correct":21},"C","资金准备",true,{"key":23,"text":24,"correct":14},"D","施工队伍准备","施工准备阶段的安全技术措施有：技术准备、物资准备、施工现场准备、施工队伍准备。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]