[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1165744":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1165744,827,2,"多选题","建筑起重机械安装前安装单位应当将建筑起重机械安装、拆卸工程专项施工方案,安装、拆卸人员名单,安装、拆卸时间等材料报( )审核后,告知工程所在地县级以上地方人民政府建设主管部门。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工总承包单位",true,{"key":16,"text":17,"correct":18},"B","使用单位",false,{"key":20,"text":21,"correct":18},"C","租赁单位",{"key":23,"text":24,"correct":14},"D","监理单位",{"key":26,"text":27,"correct":18},"E","维修单位","AD","",{"id":6,"name":31,"category":32,"favorite":33},"岗位技能","建筑工程",0]