[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1165660":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1165660,827,2,"多选题","常用高层建筑施工起重运输体系组合情况包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","塔式起重机+施工电梯",true,{"key":16,"text":17,"correct":14},"B","塔式起重机+施工电梯+混凝土泵车",{"key":19,"text":20,"correct":14},"C","塔式起重机+施工电梯+拖式混凝土泵",{"key":22,"text":23,"correct":24},"D","塔式起重机+混凝土泵车+拖式混凝土泵",false,{"key":26,"text":27,"correct":24},"E","塔式起重机+拖式混凝土泵","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"岗位技能","建筑工程",0]