[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1165079":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1165079,826,2,"多选题","某建筑工地需用3台800kN·m塔式起重机。总承包单位与一家起重机械安装单位签订了安装合同。 安装前应进行检查，包括（ ）检查内容。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑机械",true,{"key":16,"text":17,"correct":18},"B","资金到位情况",false,{"key":20,"text":21,"correct":14},"C","现场施工条件",{"key":23,"text":24,"correct":18},"D","土建工程质量",{"key":26,"text":27,"correct":18},"E","合同利润情况审查","AC","安装前应进行检查，包括建筑机械、现场施工条件检查内容。",{"id":6,"name":31,"category":32,"favorite":33},"(机械员)专业管理实务 岗位知识","建筑工程",0]