[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1164983,826,1,"单选题","当施工升降机安装、拆卸过程中专项施工方案发生变更时，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按程序重新对方案进行审批",true,{"key":16,"text":17,"correct":18},"B","按程序重新对方案进行修改",false,{"key":20,"text":21,"correct":18},"C","按程序重新对方案进行完善",{"key":23,"text":24,"correct":18},"D","按程序重新编制方案","当施工升降机安装、拆卸过程中专项施工方案发生变更时，应按程序重新对方案进行审批。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]