[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1164717,826,1,"单选题","建筑起重机械安装、拆卸工程应由安装单位编制专项方案，并由安装单位（ ）签字。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术负责人",true,{"key":16,"text":17,"correct":18},"B","法定代表人",false,{"key":20,"text":21,"correct":18},"C","总经理",{"key":23,"text":24,"correct":18},"D","项目经理","建筑起重机械安装、拆卸工程应由安装单位编制专项方案，并由安装单位技术负责人签字。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]