[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1164654,826,1,"单选题","工地临时用电线路较长，用电设备较多，临时用电安全是施工顺利进行的保障。请根据实际情况回答下列问题。 经计算，照明线路的负荷电流为10 A，选择熔丝的额定电流应为（ ）A。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7.5",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","20","经计算，照明线路的负荷电流为10A，选择熔丝的额定电流应为12A。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]