[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1164653,826,1,"单选题","在施工现场专用变压器的供电的TN-s接零保护系统中，电气设备的金属外壳（ ）与保护零线连接。保护零线应由工作接地线、配电室（总配电箱）电源侧零线或总漏电保护器电源侧零线处引出。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不应",false,{"key":16,"text":17,"correct":14},"B","不得",{"key":19,"text":20,"correct":21},"C","必须",true,{"key":23,"text":24,"correct":14},"D","可以","在施工现场专用变压器的供电的TN-s接零保护系统中，电气设备的金属外壳必须与保护零线连接。保护零线应由工作接地线、配电室（总配电箱）电源侧零线或总漏电保护器电源侧零线处引出。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]