[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1164647,826,1,"单选题","施工现场临时用电设备在（ ）台及以上或设备总容量在（ ）KW及以上者，应编制用电组织设计。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","（5，50）",true,{"key":16,"text":17,"correct":18},"B","（6，60）",false,{"key":20,"text":21,"correct":18},"C","（7，70）",{"key":23,"text":24,"correct":18},"D","（8，80）","施工现场临时用电设备在5台及以上或设备总容量在50KW及以上者，应编制用电组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]