[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1164614,826,1,"单选题","当绝缘隔离防护措施无法实现时，必须与有关部门协商，采取停电、迁移外电线路或改变工程位置等措施，未采取上述措施的（ ）施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","严禁",true,{"key":16,"text":17,"correct":18},"B","可以",false,{"key":20,"text":21,"correct":18},"C","应该",{"key":23,"text":24,"correct":18},"D","能够","当绝缘隔离防护措施无法实现时，必须与有关部门协商，采取停电、迁移外电线路或改变工程位置等措施，未采取上述措施的严禁施工。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]