[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1164595,826,1,"单选题","临时用电工程应定期检查。定期检查时，应复查（ ）电阻值和绝缘电阻值。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","接线",false,{"key":16,"text":17,"correct":14},"B","接触",{"key":19,"text":20,"correct":21},"C","接地",true,{"key":23,"text":24,"correct":14},"D","连接","临时用电工程应定期检查。定期检查时，应复查接地电阻值和绝缘电阻值。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]