[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1164593,826,1,"单选题","临时用电组织设计及变更用电时，必须履行“（ ）”程序，由电气工程技术人员组织编制，经相关部门审核及具有法人资格企业的技术负责人批准后实施。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制",false,{"key":16,"text":17,"correct":14},"B","审核",{"key":19,"text":20,"correct":14},"C","批准",{"key":22,"text":23,"correct":24},"D","三项都是",true,"临时用电组织设计及变更用电时，必须履行“编制、审核、批准”程序5由电气工程技术人员组织编制，经相关部门审核及具有法人资格企业的技术负责人批准后实施。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]