[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1164581,826,1,"单选题","施工机械变动成本中，（ ）支出较大，是管理重点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","配件费",false,{"key":16,"text":17,"correct":18},"B","动力、燃料费",true,{"key":20,"text":21,"correct":14},"C","保养费",{"key":23,"text":24,"correct":14},"D","人员工资","施工机械变动成本中，动力、燃料费支出较大，是管理重点。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]