[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164476":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1164476,826,1,"单选题","应急购置计划中应说明（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","购置理由",true,{"key":16,"text":17,"correct":18},"B","机械名称",false,{"key":20,"text":21,"correct":18},"C","规格",{"key":23,"text":24,"correct":18},"D","数量","因工程需要，超出年度购置计划紧急采购施工设备时，应编制应急购置计划（报告）。应急购置计划中应说明购置理由。应急购置计划的审批程序同年度机械购置计划。应急购置计划是对年度购置计划的调整和补充。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]