[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164462":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1164462,826,1,"单选题","收搜集资料，掌握有关装备情况，根据计划任务测算需求，是编制年度机械购置、租赁计划的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","准备阶段",true,{"key":16,"text":17,"correct":18},"B","平衡阶段",false,{"key":20,"text":21,"correct":18},"C","选择论证阶段",{"key":23,"text":24,"correct":18},"D","确定阶段","年度机械购置、租赁计划的编制程序准备阶段。收搜集资料，掌握有关装备情况，根据计划任务，测算需求。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)专业管理实务 岗位知识","建筑工程",0]