[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164339":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1164339,825,3,"判断题","综合单价适用于分部分项工程量清单，不适用于措施项目清单、其他项目清单等",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"综合单价不但适用于分部分项工程量清单，也适用于措施项目清单、其他项目清单等。",{"id":6,"name":21,"category":22,"favorite":23},"(机械员)基础知识","建筑工程",0]