[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164058":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1164058,825,2,"多选题","某包工包料的住宅楼电气设备安装工程，主要进行住宅楼的照明和防雷接地的安装。施工中需要进行脚手架的搭拆与一定的夜间加班赶工，试问： 综合单价的构成是完成一个规定计量单位所需的（ ），并考虑风险因素。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人工费、材料费、机械费",true,{"key":16,"text":17,"correct":14},"B","管理费",{"key":19,"text":20,"correct":21},"C","规费",false,{"key":23,"text":24,"correct":21},"D","税金",{"key":26,"text":27,"correct":14},"E","利润","ABE","综合单价的构成是完成一个规定计量单位所需的人工费、材料费、机械费、管理费、利润，并考虑风险因素。",{"id":6,"name":31,"category":32,"favorite":33},"(机械员)基础知识","建筑工程",0]