[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164056":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1164056,825,2,"多选题","《建设工程工程量清单计价规范》中实行了（ ）统一",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分部分项工程项目名称",true,{"key":16,"text":17,"correct":14},"B","计量单位",{"key":19,"text":20,"correct":14},"C","工程量计算规则",{"key":22,"text":23,"correct":14},"D","项目编码",{"key":25,"text":26,"correct":27},"E","统一计划利润率",false,"ABCD","《建设工程工程量清单计价规范》中实行了分部分项工程项目名称、计量单位、工程量计算规则、项目编码统一",{"id":6,"name":31,"category":32,"favorite":33},"(机械员)基础知识","建筑工程",0]