[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164055":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1164055,825,2,"多选题","工程量清单由（ ）构成。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",true,{"key":16,"text":17,"correct":14},"B","措施项目清单",{"key":19,"text":20,"correct":14},"C","其他项目清单",{"key":22,"text":23,"correct":24},"D","工程定额",false,{"key":26,"text":27,"correct":24},"E","工程量","ABC","工程量清单由包括分部分项工程量清单、措施项目清单、其他项目清单构成。",{"id":6,"name":31,"category":32,"favorite":33},"(机械员)基础知识","建筑工程",0]