[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1164048":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1164048,825,2,"多选题","《建设工程工程量清单计价规范》附录的表现形式是以表格形式现的，其内容除项目编码、项目名称外，还应有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目特征",true,{"key":16,"text":17,"correct":14},"B","工程内容",{"key":19,"text":20,"correct":21},"C","工程量",false,{"key":23,"text":24,"correct":14},"D","计量单位",{"key":26,"text":27,"correct":14},"E","工程量计算规则","ABDE","《建设工程工程量清单计价规范》附录的表现形式是以表格形式现的，其内容除项目编码、项目名称外，还应有项目特征、工程内容、计量单位、工程量计算规则。",{"id":6,"name":31,"category":32,"favorite":33},"(机械员)基础知识","建筑工程",0]