[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163991":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1163991,825,2,"多选题","目钢网架的高空散拼法吊装，主要施工流程有：吊装机械的选择、（ ）等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","构件准备",true,{"key":16,"text":17,"correct":14},"B","搭设拼装台",{"key":19,"text":20,"correct":21},"C","设置滑道",false,{"key":23,"text":24,"correct":14},"D","构件拼装",{"key":26,"text":27,"correct":14},"E","拆除拼装台","ABDE","高空散拼法吊装，主要施工流程有：根据结构的外形尺寸、构件重量、现场环境等综合因素考虑吊装机械的选择。高空散拼法由于吊装面积大、高空作业多、吊装构件不是很重的特点，一般宜选用机械操纵灵活，运行方便，作业面积大的吊装设备；构件准备。网架的各种构件进场后，要进行构件规格尺寸的检验，并编写构件代号单独堆放，以方便吊装；在现场加工的杆件要实行加工前正确放线，加工后复验，吊装前再复验的三检尺制度。；搭设拼装台。",{"id":6,"name":31,"category":32,"favorite":33},"(机械员)基础知识","建筑工程",0]