[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1163917,825,1,"单选题","根据《安全生产管理条例》，以下哪项不属于需要编制专项施工方案的工程（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","模板工程",false,{"key":16,"text":17,"correct":14},"B","脚手架工程",{"key":19,"text":20,"correct":14},"C","土方开挖工程",{"key":22,"text":23,"correct":24},"D","水电安装工程",true,"《安全生产管理条例》第26条规定施工单位应当在施工组织设计申编制安全技术措施和施工现场临时用电方案。同时规定：对下列达到一定规模的危险性较大的分部分项工程编制专项施工方案：A．基坑支护与降水工程；B．土方开挖工程；C．模板工程；D．起重吊装工程；E．脚手架工程；F．拆除、爆破工程；G．国务院建设行政主管部门或者其他有关部门规定的其他危险性较大的工程。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)基础知识","建筑工程",0]