[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1163758,825,1,"单选题","新安装或转移工地重新安装以及经过大修后的升降机，（ ），必须经过坠落试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在投入使用前",true,{"key":16,"text":17,"correct":18},"B","使用后一个月",false,{"key":20,"text":21,"correct":18},"C","使用2个月",{"key":23,"text":24,"correct":18},"D","使用后3天","新安装或转移工地重新安装以及经过大修后的升降机，在投入使用前，必须经过坠落试验。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)基础知识","建筑工程",0]