[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1163734,825,1,"单选题","静压桩机操作中不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当桩的贯人力太大，使桩不能压至标高时应及时增加配重",true,{"key":16,"text":17,"correct":18},"B","当桩顶不能最后压到设计标高时，应将桩顶部分凿去。不得用桩机行走的方式，将桩强行推断",false,{"key":20,"text":21,"correct":18},"C","当压桩引起周围土体隆起，影响桩机行走时，应将桩机前进方向隆起的土铲平，不得强行通过",{"key":23,"text":24,"correct":18},"D","压桩机在顶升过程中，船形轨道不应压在已人土的单一桩顶上","当桩的贯人阻力太大，使桩不能压至标高时，不得任意增加配重。应保护液压元件和构件不受损坏。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)基础知识","建筑工程",0]