[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1163707,825,1,"单选题","全套管钻机浇筑混凝土时，钻机操作应和灌注作业密切配合，应根据孔深、桩长适当配管，套管与浇筑管保持同心，在浇注管埋人混凝土（ ）m之间时，应同步拔管和拆管，并应确保浇筑成桩质量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1~2",false,{"key":16,"text":17,"correct":14},"B","2~3",{"key":19,"text":20,"correct":21},"C","2~4",true,{"key":23,"text":24,"correct":14},"D","3~4","全套管钻机浇筑混凝土时，钻机操作应和灌注作业密切配合，应根据孔深、桩长适当配管，套管与浇筑管保持同心，在浇注管埋人混凝土2~4m之间时，应同步拔管和拆管，并应确保浇筑成桩质量。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)基础知识","建筑工程",0]