[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1163657,825,1,"单选题","建设单位根据决算编制要求，工程建设项目从筹建到交付使用所需的全部建设费用称为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","结算",false,{"key":16,"text":17,"correct":14},"B","预算",{"key":19,"text":20,"correct":14},"C","核算",{"key":22,"text":23,"correct":24},"D","决算",true,"决算：是建设单位根据决算编制要求，工程建设项目从筹建到交付使用所需的全部建设费用。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)基础知识","建筑工程",0]