[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1163651,825,1,"单选题","工程量清单计价是指投标人完成由招标人提供的工程量清单所需的全部费用，不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费",false,{"key":16,"text":17,"correct":14},"B","措施项目费和其他项目费管理费",{"key":19,"text":20,"correct":21},"C","利润",true,{"key":23,"text":24,"correct":14},"D","规费、税金","工程量清单计价是指投标人完成由招标人提供的工程量清单所需的全部费用，不包括利润。",{"id":6,"name":27,"category":28,"favorite":29},"(机械员)基础知识","建筑工程",0]