[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163237":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1163237,824,2,"多选题","招标工程量清单的组成内容主要包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单表",true,{"key":16,"text":17,"correct":14},"B","措施项目清单",{"key":19,"text":20,"correct":21},"C","单位工程量清单",false,{"key":23,"text":24,"correct":14},"D","规费、税金项目清单表",{"key":26,"text":27,"correct":14},"E","补充工程量清单、项目及计算规则表","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"通用基础","建筑工程",0]