[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1163100,824,1,"单选题","以下关于施工项目目标控制的表述,错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工项目目标控制问题的要素包括施工项目、控制目标、控制主体、实施计划、实施信息、偏差数据、纠偏措施、纠偏行为",false,{"key":16,"text":17,"correct":14},"B","施工项目控制的目的是排除干扰、实现合同目标",{"key":19,"text":20,"correct":14},"C","施工项目目标控制是实现施工目标的手段",{"key":22,"text":23,"correct":24},"D","施工项目目标控制包括进度控制、质量控制和成本控制三个方面",true,"",{"id":6,"name":27,"category":28,"favorite":29},"通用基础","建筑工程",0]