[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1163063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1163063,824,1,"单选题","需要对不同砂浆、混凝土强度等级进行换算时,需要根据( )进行材料费的调整。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人工费",false,{"key":16,"text":17,"correct":14},"B","机械费",{"key":19,"text":20,"correct":14},"C","材料用量",{"key":22,"text":23,"correct":24},"D","强度等级",true,"",{"id":6,"name":27,"category":28,"favorite":29},"通用基础","建筑工程",0]