[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1162932,824,1,"单选题","为了取得施工成本管理的理想效果,必须从多方面采取有效措施实施管理,这些措施不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","管理措施",true,"",{"id":6,"name":27,"category":28,"favorite":29},"通用基础","建筑工程",0]