[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162716":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162716,823,2,"多选题","工程成本核算的依据为( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","会计核算",true,{"key":16,"text":17,"correct":14},"B","业务核算",{"key":19,"text":20,"correct":14},"C","统计核算",{"key":22,"text":23,"correct":24},"D","年度核算",false,{"key":26,"text":27,"correct":24},"E","月度核算","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"岗位技能","建筑工程",0]