[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1162540,823,1,"单选题","现场剩余材料的主要处置措施不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因建设单位设计变更,造成多余材料的积压,经协商后余料退回建设单位",false,{"key":16,"text":17,"correct":14},"B","工程的剩余物资冲减原项目工程成本",{"key":19,"text":20,"correct":14},"C","竣工后的剩余物资经协商后冲减原项目I程成本",{"key":22,"text":23,"correct":24},"D","工程竣工后废旧物资,由原项目的项目经理负责处理",true,"",{"id":6,"name":27,"category":28,"favorite":29},"岗位技能","建筑工程",0]