[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162449":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1162449,822,3,"判断题","单位工程机械需用（台班）量确定的依据是单位工程工程量和定额机械台班用量。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"设备需用量的计算单位工程施工机械需用（台班）量计算是根据单位工程工程量、施工方案、施工机具类型、定额机械台班用量编制的。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]