[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162415":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1162415,822,3,"判断题","建设工程物资采购合同一般分为材料采购合同和设备采购合同，两者的区别主要在于资金占用率不同。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"物资采购合同可分为建筑材料采购合同和设备采购合同，合同当事人为供方和需方。供方应对其生产或供应的产品质量负责，而需方则应根据合同的规定进行验收。建筑材料采购合同的主要内容．包括标的、数量、包装、交付及运输方式、验收、交货期限、价格、结算、违约责任。设备采购合同的主要内容，包括设备价格与支付、设备数量、技术标准、现场服务、验收和保修。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]