[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162408":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1162408,822,3,"判断题","对于一些通用性材料，在工程进行初期阶段，考虑到可能出现的施工进度超额因一般都略加大储备，其实际需用量就略大于计划需用量。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"对于一些通用性材料，在工程进行初期阶段，考虑到可能出现的施工进度超额因一般都略加大储备，其实际需用量就略大于计划需用量。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]