[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162395":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1162395,822,3,"判断题","考虑到“工完料清场地净”，材料实际需用量要略小于计划需用量。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"在工程竣工阶段，因考虑到“工完料清场地净”，防止工程竣工材料积压，一般是利用库存控制进料，这样实际需用量要略小于计划需用量。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]