[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162362":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1162362,822,3,"判断题","凡属于施工组织设计以内的工程暂设用料，一律按工长填制、项目经理审批的“工程暂设用料申请单\\\"作为发料依据。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"凡属于施工组织设计以内的工程暂设用料，一律按工程用料以限额领料单作为发料依据。施工组织设计以外的临时零星用料，则须凭工长填制、项目经理审批的《工程暂设用料申请单》办理领料手续。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]