[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162297":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1162297,822,3,"判断题","按单位工程实行限额领料有利于工种的配合和工序衔接，有利于调动各方面积极性。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"限额领料的形式有1、按分项工程实行限额领料2、按工程部位实行限额领料3、按单位工程实行限额领料\\n其中按分项工程实行限额领料即按照分项工程进行限额，如钢筋绑扎、混凝土浇筑、砌筑、抹灰等，它是以施工班组为对象进行的限额领料。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]