[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162264":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1162264,822,3,"判断题","承包人可以将其承包的全部建设工程转包给第三人，但不得将其承包的全部建设工程肢解以后以分包的名义分别转包给第三人。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"承包人不得将其承包的全部建设工程转包给第三人或将其承包的全部建设工程肢解以后以分包的名义分别转包给第三人。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]