[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162239":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1162239,822,3,"判断题","F1DIC施工合同条件中规定的合同有效期，是指从工程师按合同约定发布的“开工令\\\"中指明的应开工之日起，至工程接收证书注明的竣工日止的日历天数。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"本题考核的知识点为施工期。施工期从工程师按合同约定发布的“开工令”中指明的应开工之日起，至工程接收证书注明的竣工日止的日历天数为承包商的施工期。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)专业管理实务 岗位知识","建筑工程",0]